Section 19

SITE CLOSURES
Interim Final – January 2021

Click to jump to your area of interest or scroll down to read about this topic.
Section 19.0 INTRODUCTION

Section 19.1 SITE CLOSURE SCOPING
19.1.1 Evaluation of Future Land Use
19.1.2 Remedy Selection and Site Closure Implications

Section 19.2 UNRESTRICTED CLOSURES
19.2.1 No Action
19.2.2 No Further Action
19.2.3 Letter of Completion

Section 19.3 CLOSURES WITH USE RESTRICTIONS
19.3.1 No Further Action with Restrictions
19.3.2 Letter of Completion with Restrictions

Section 19.4 NO FURTHER ACTIVE REMEDIATION LETTER

Section 19.5 ENVIRONMENTAL HAZARD EVALUATION (EHE)

Section 19.6 ENVIRONMENTAL HAZARD MANAGEMENT PLAN (EHMP)
19.6.1 Basic Components for all EHMPs
19.6.2 Site-Specific EHMPs
19.6.3 Programmatic (Area-wide) EHMPs
19.6.4 Construction EHMPs

Section 19.7 INSTITUTIONAL AND ENGINEERING CONTROLS
19.7.1 Institutional Controls
19.7.2 Engineering Controls

Section 19.8 LEGAL INSTRUMENTS FOR RESTRICTED USE CLOSURES
19.8.1 Uniform Environmental Covenants Act (UECA) Environmental Covenant
19.8.2 Voluntary Response Program (VRP) Letter of Completion (LOC)
19.8.3 DoD Land Use Controls Implementation Plans
19.8.4 Property Transfers and Site Closures with Use Restrictions

Appendix 19-A Long-Term Management of Petroleum-Contaminated Soil and Groundwater.

Return to the Top of the Page

19.0 SITE CLOSURES

Under the Hawaiʻi State Contingency Plan (SCP) [i.e., Hawaiʻi Administrative Rules (HAR), Title 11, Chapter 451 (HAR Chapter 11-451)] an unrestricted site closure is granted as a “No Further Action”, once the Hazard Evaluation and Emergency Response Office (HEER Office) of the State of Hawaiʻi Department of Health (HDOH) decides that no further action is necessary for a specific release, suspected release, or upon the successful completion of a response action (either removal or remedial action). If contaminated media remains on site that necessitates land use restrictions, a “No Further Action with Restrictions” is granted. The HEER Office also may issue “No Action” determinations if sampling data indicate no evidence of a release, or the documented release is judged by the HEER Office as not warranting cleanup or restriction.

An unrestricted site closure approved under the Voluntary Response Program (VRP) is granted as a “Letter of Completion” (LOC). If contaminated media remains on site necessitating land use restrictions, a “Letter of Completion with Restrictions” is granted.

Note that a restriction is distinct from a condition. All LOCs have conditions, but they may not be “restrictions” (for example, a site with a LOC allowing unrestricted use will have a condition that requires the LOC be noted on the deed and sent to the County agency that issues building permits).

Thus, the available types of site closures include:

  • No Action
  • No Further Action
  • No Further Action with Restrictions
  • Letter of Completion (under VRP)
  • Letter of Completion with Restrictions (under VRP)

The HEER Office may also issue a “No Further Active Remediation Letter;” however, this is not a type of site closure. No Further Active Remediation status is intended for contaminated sites where potentially significant environmental concerns remain, but active remediation (e.g., excavation, soil vapor extraction, etc.) is no longer practical. This status may be helpful to site owners, financial institutions, and potential purchasers to establish the “environmental liability” of a site with remaining contamination prior to formal site closure.

Within the various types of site closures a number of possible outcomes exist, ranging from clean closures with no land use restrictions to containment-based remedies addressing contaminated media left on site with monitoring requirements and stringent land use restrictions.

The type of site closure being sought must be selected prior to or during the response action selection stage. To ensure the restrictions and limitations that will result from the selected type of closure are feasible and/or acceptable to stakeholders, use systematic planning processes (see Section 3) to guide the site closure process, keeping long-term use of the site in mind.

Return to the Top of the Page

19.1 SITE CLOSURE SCOPING

Site closure scoping is an important step that includes evaluating future land uses and determining site closure implications of the selected remedy. Site closure scoping can be part of the removal action work plan/removal action alternatives analysis (see Section 14), or the remedial alternatives analysis/response action memorandum (see Section 16).

Return to the Top of the Page

19.1.1 EVALUATION OF FUTURE LAND USE

Planning or knowledge regarding future land use is crucial to evaluating site closure decisions. Evaluating future land use typically involves reviewing available records, determining current land use, inspecting the site and surrounding area, and discussing future uses with local government officials, current and future property owners, and the community. Further information about evaluating future land use is available from the United States Environmental Protection Agency (USEPA, 2001d).

Return to the Top of the Page

19.1.2 REMEDY SELECTION AND SITE CLOSURE IMPLICATIONS

During the remedial alternatives analysis (for remedial response actions), remedies undergo a comparative analysis that focuses on the performance of each remedial alternative against three criteria: (1) Effectiveness, (2) Implementability, and (3) Cost (see Section 16). In addition, all potential remedial alternatives, except the required No Action alternative, must meet the threshold criterion of being protective of human health and the environment.

Considering the post-closure implications of each remedial option is essential to properly evaluating long-term effectiveness, implementability, and cost. Several issues must be considered to attain a site closure that is acceptable for the planned future site use and to the stakeholders involved.

Issues to consider during remedy selection and evaluation of post-closure implications include:

  • Will the remedy restrict future land (or groundwater) use at the site?
  • Will stakeholders concur with the land use restrictions?
  • Will current and future property owners commit to implementing and maintaining the land use restrictions?
  • What practices and safeguards will need to be implemented and maintained to ensure safe use of the property?
  • Will the remedy compromise the architectural integrity of on-site structures?
  • How will land use restrictions affect the property value? For example, will financial institutions be wary of loaning funds to prospective purchasers in future real estate transactions if contaminated soil and/or groundwater remains on site?
  • What will be the long-term costs of institutional and engineering controls associated with managing contamination on site?
  • What long-term effectiveness can be expected of the institutional and engineering controls? For example, will institutional controls (e.g., an environmental covenant) and engineering controls (e.g., a visible marker or boundary layer) be effective in preventing future site occupants from digging into contaminated soil or groundwater?
  • What potential legal liabilities may be caused by managing contaminated soil or groundwater on site? Are landowners and other stakeholders willing to accept those liabilities?
  • Will an exemption of liability for prospective purchasers granted for voluntary response actions (if the cleanup is completed under the VRP) increase the value of the property? Will an increase in value outweigh any additional costs associated with participating in the VRP?

Containment Remedies

Remedies that leave hazardous substances remaining on site as a permanent solution are known as containment remedies, because the hazardous substances are not removed or destroyed, but only contained. Containment remedies prevent hazardous substances from impacting public health or the environment only as long as they are maintained. Use of containment remedies will necessitate land use restrictions at the site.

If a containment remedy is being evaluated, the potential for it to fail over the long-term should be closely assessed. Several examples of potential remedy failures include:

  • Failing to continue operation and maintenance of an active engineering control, such as an active vapor mitigation system.
  • Failing to implement, maintain, and report on required monitoring.
  • Failing to notify construction workers, tenants, etc. of use restrictions.
  • Failing to prevent forbidden land uses, such as allowing residential use of land or soil cleaned up only to commercial/industrial Environmental Action Levels (EALs).
  • Actively breaching a passive engineering control, such as digging through a protective soil layer, barrier, or visible marker into contaminated soil.
  • Failing to incorporate protective systems designed to prevent exposure, such as constructing a new building on the site without the necessary vapor mitigation measures.
  • Sale of the property without appropriate disclosures

Containment can be the least expensive remedy in terms of initial capital costs. However, when all of the associated costs are included (such as institutional control development, preparation and implementation of an Environmental Hazard Management Plan (EHMP), long-term monitoring costs, long-term operation of engineering controls, future incremental costs of managing contaminated materials, depreciation of land value, and maintenance costs), containment remedies typically have comparable costs to treatment remedies or removal actions. These long-term costs should be included in the Removal or Remedial Alternatives Analyses. The potential consequences of containment remedy selection include:

  • Continued reporting
  • Continued cost for monitoring and operation and maintenance
  • May be ordered to take action under Hawaiʻi Revised Statutes (HRS), Chapter 128D (HRS 128D) (the state government)
  • May be ordered to take action under the Comprehensive Environmental Response, Compensation, and Liability Act (CERCLA) (the federal government)
  • Vulnerable to third-party torts if people claim harm
  • Continued listing on state cleanup site lists
  • Continued visibility to the community as a cleanup site with existing contamination
  • Site flagged by Phase I Environmental Site Assessments
  • Site listed as a liability on corporate balance sheets under Sarbanes-Oxley reporting
  • Site property value decreased
  • Less attractive to developers due to environmental protections needed for construction
  • Engineering controls make future construction more difficult (e.g., concrete caps)
  • Residual contamination may subject future construction workers to exposure hazards

In summary, remedial options must be thoroughly evaluated to determine the post-closure implications of each. Selection of a site closure option acceptable to the stakeholders involved will expedite the process and avoid costly and unnecessary delays.

Return to the Top of the Page

19.2 UNRESTRICTED CLOSURES

If contaminated media is removed or treated to concentrations below the Tier 1 EALs or alternate action levels approved by the HEER Office, the site may be closed with unrestricted use (i.e., a No Action, a No Further Action, or a Letter of Completion).

Return to the Top of the Page

19.2.1 NO ACTION

The HEER Office may, at its discretion, elect to review and provide determinations on sites where a property owner or prospective purchaser suspected a release that was disconfirmed by appropriate sampling data. In such cases, a No Action letter may be granted by the HEER Office. Examples include Phase II sampling to investigate an identified “recognized environmental condition” and appropriate screening of former agricultural fields for pesticide contamination. In cases where representative sampling indicates that contaminant levels are present above natural background levels but below applicable EALs, the HEER Office may elect to issue a No Further Action letter rather than a No Action letter.

Return to the Top of the Page

19.2.2 NO FURTHER ACTION

An unrestricted site closure under the Hawaiʻi SCP (HAR Chapter 11-451) is granted as a No Further Action (NFA). Once the HEER Office decides that no further action is necessary for a specific release, suspected release, or upon the successful completion of a response action (either removal or remedial action), a NFA letter will be sent to the responsible party(s) and the property owner. If the response action has resulted in either (1) removal of impacted media or (2) treatment of impacted media to concentrations below EALs for a residential land use scenario and any ecological concerns, the site closure is referred to as a “clean closure” or an “unrestricted closure.” No land use restrictions are necessary and the site can be used for all potential future land uses. No further reporting requirements are necessary to HDOH. If new information indicates that contamination is present at levels of concern, the HEER Office may re-open the site and require additional assessment and cleanup work (as necessary) to be performed.

Return to the Top of the Page

19.2.3 LETTER OF COMPLETION

An unrestricted site closure under the VRP (HRS 128D, Part II) is granted as a LOC. The purpose of the VRP is to minimize environmental liability and assure timely HEER Office oversight in a way that will encourage prospective developers, lenders, and purchasers to voluntarily clean up properties. The VRP facilitates the cleanup process and, in certain situations, provides relief from the strict liability provisions of the Federal CERCLA and Hawaiʻi Environmental Response Laws. The greatest benefit to a site closure under the VRP is exemption of future liability for prospective purchasers and developers for the specific hazardous substances, pollutants, contaminants, media, and land area addressed in the voluntary response action, as specified in the LOC. An existing landowner does not receive relief from the strict liability provisions by undertaking a VRP cleanup; these protections extend only to prospective purchasers, future owners, operators, and tenants.

Following receipt of an unrestricted LOC, the site can be used for all potential future land uses. No further reporting to the HDOH is required. The LOC is noted on the property deed and is sent to the county agency that issues building permits. The LOC “runs with the land” and applies to all future owners of the property.

HDOH may only order a prospective purchaser who receives a LOC to re-open the site if future information indicates that contamination is present at levels of concern (above Tier 1 EALs) for contaminants and media not listed in the LOC and VRP Agreement, or if a new release of contaminants and media listed in the LOC and VRP agreement occurs after the LOC is signed.

Return to the Top of the Page

19.3 CLOSURES WITH USE RESTRICTIONS

If contaminated media is left on site necessitating institutional or engineering controls to prevent potential future exposures, the site is closed with restricted use (i.e., a No Further Action with Restrictions or a Letter of Completion with Restrictions). The potential environmental hazards posed by leaving contaminated media on site must be assessed and documented in an Environmental Hazard Evaluation (EHE) (see Subsection 19.5). The mechanism to manage the environmental hazards posed by contaminated media left on site is called an EHMP (see Subsection 19.6).

A typical example of a restricted use closure is a petroleum-release site where petroleum-impacted soil cannot be fully excavated from the site (e.g., petroleum-impacted soil cannot be removed without jeopardizing structural integrity of a building). In the example, soil gas samples would need to be collected from beneath the slab, and resulting data may indicate a potential environmental hazard from subsurface vapor intrusion into indoor air spaces. The site may be closed with restricted use, but engineering controls (e.g., an active vapor mitigation system); institutional controls (i.e., an environmental covenant to restrict land use) may be necessary to prevent future exposures. An EHE would be required to assess potential hazards posed by the remaining petroleum contaminated soil. An EHMP would be required to document and manage the residual contaminated soil, engineering controls, and institutional controls. The EHMP typically would be attached to the closure document and, if applicable, the environmental covenant (see Subsection 19.8.1).

Another example of a restricted use closure is a case where only a land use restriction is required, with no engineering controls. This may be commonly applied in situations where representative contaminant levels are above the soil or groundwater “residential use” EALs, but below applicable “commercial/industrial use” EALs at a site zoned for commercial or industrial use. In this case, the site closure restriction would allow only a commercial/industrial use of the property, until such time as additional site investigation or site remediation demonstrates contaminant levels are below EALs for residential or unrestricted use. As noted in the example above, an EHPM typically would be attached to the closure document and, if applicable, the environmental covenant, to help document and manage the institutional controls at the site (e.g., the land use restrictions).

Return to the Top of the Page

19.3.1 NO FURTHER ACTION WITH RESTRICTIONS

A restricted use closure under the Hawaiʻi SCP (HAR Chapter 11-451) is granted as a NFA with Restrictions. If the removal or remedial action has resulted in leaving contaminated media on site, the site closure is referred to as a “restricted use closure.” An EHE must be prepared to document and assess environmental hazards posed by the remaining contaminated media. Institutional and/or engineering controls are necessary to prevent future exposures; therefore, future land uses are restricted. An EHMP is necessary to manage the residual contamination, engineering controls, and/or institutional controls.

Return to the Top of the Page

19.3.2 LETTER OF COMPLETION WITH RESTRICTIONS

A restricted use closure under the VRP (HRS 128D, Part II) is granted as a LOC with Restrictions. An EHE must be prepared to document and assess environmental hazards posed by the remaining contaminated media. Institutional and/or engineering controls are necessary to prevent future exposures; therefore, future land uses are restricted. An EHMP is necessary to manage the residual contamination, engineering controls, and/or institutional controls. Long-term (periodic) monitoring and reporting may be required to the HEER Office.

The LOC with Restrictions is noted on the property deed and is sent to the county agency that issues building permits. The restrictions on the LOC “run with the land” and apply to all future owners of the property.

HDOH may order a prospective purchaser receiving a LOC to re-open the site only if institutional or engineering controls that are part of the LOC are not being maintained, or contaminant concentrations are discovered at levels of concern (above Tier 1 EALs) for contaminants and media not listed in the LOC and VRP Agreement, or if a new release of contaminants and media listed in the LOC and VRP agreement occurs after the LOC is signed. HDOH cannot require prospective purchasers to perform additional work for contaminants and media covered in the VRP Agreement, as they have exemption from liability under HRS 128D, Part II.

Return to the Top of the Page

19.4 NO FURTHER ACTIVE REMEDIATION LETTER

A No Further Active Remediation Letter is available for contaminated sites where potentially significant, environmental concerns remain but active remediation (e.g., excavation, soil vapor extraction, etc.) is no longer practical. This type of letter is often used when further excavation can jeopardize the structural integrity of buildings. If needed, a letter may be requested from the HEER Office indicating that No Further Active Remediation is required at such a site.

A No Further Active Remediation status is not considered a type of site closure. The case will remain “open” in the HEER Office site records. The letter is intended to clarify that all major cleanup actions have been completed at the site, but significant contamination remains and the site has moved into a status of long-term monitoring and management. This status may be helpful to site owners, financial institutions, and potential purchasers to establish the “environmental liability” of a site with remaining contamination prior to formal site closure. The No Further Active Remediation letter may also contain conditions of further work when (or if) the site is redeveloped. The need for on-going groundwater monitoring or soil gas monitoring may indicate a No Further Active Remediation Letter is not yet appropriate.

An EHE must be prepared to document and assess the remaining contamination. An EHMP must be prepared to manage the contamination, engineering controls, and/or institutional controls. The EHMP must include a description of conditions that must be met before the site can be formally closed with status of either No Further Action or a No Further Action with Restrictions.

Additional information regarding No Further Active Remediation letters is presented in HDOH guidance on Long-Term Management of Petroleum-Contaminated Soils and Groundwater (HDOH, 2007c; included as Appendix 19-A). This document outlines procedures for long-term management of residual petroleum contamination where a full cleanup is not practicable. The guidance document includes discussion and figures providing decision trees to address long-term oversight of residual petroleum contamination.

Return to the Top of the Page

19.5 ENVIRONMENTAL HAZARD EVALUATION (EHE)

Environmental Hazard Evaluation (EHE) is the link between site investigation activities and response actions. In addition, if contaminated media is left on site under a restricted use closure, the EHE is necessary to assess and document potential environmental hazards posed by the contamination. Results of the EHE are crucial in selecting the appropriate measures, such as engineering and/or institutional Controls, to prevent future exposures. Section 13 presents a detailed discussion on the preparation of an EHE.

Return to the Top of the Page

19.6 ENVIRONMENTAL HAZARD MANAGEMENT PLAN (EHMP)

If contaminated media is left onsite at concentrations that exceed the Tier 1 unrestricted use (residential) Environmental Action Levels (EALs) or alternative levels approved by the HEER Office, then an Environmental Hazard Management Plan (EHMP) must be prepared to manage the environmental hazards identified in the Environmental Hazard Evaluation (EHE) until such time that remedial actions reduce those concentrations to below levels of concern. This includes sites under a closure with institutional controls (including sites where the only control is commercial/industrial land use restriction), as well as sites that have not yet received an official closure by the regulatory authority.

An EHMP documents the presence of contaminated environmental media (e.g., soil, soil vapor, sediment, surface water, and/or groundwater) on a site at levels that could pose potential environmental concerns and describes how the contamination must be managed in the absence of remediation. The EHMP presents all necessary information in a single, user-friendly, stand-alone document that identifies:

  • Specific contaminants that have been identified to be present at the site above the most conservative unrestricted/residential-use screening criteria.
  • The approximate lateral and vertical extent of the contamination.
  • Potential environmental hazards posed by the contamination.
  • Institutional or engineering controls required to manage remaining contamination.
  • Appropriate handling and disposal instructions for contaminated media encountered during future construction or utility work.
  • Responsibilities of individual parties (owners and operators) to ensure that all requirements outlined in the EHMP are followed.

HDOH specifies three different types of EHMPs based on the specific phase and associated exposure concerns at the site:

  1. Site-Specific EHMP. Prepared for cases where site conditions have been adequately characterized and contamination is relatively localized, and either a response action has been completed, yet contamination remains in-place, or a response action has not been completed but HDOH has required and approved an interim action to manage exposure to the contamination. A site-specific EHMP typically applies to a single land parcel and can be either interim or long-term. The EHMP is typically attached to the closure document and, if applicable, to the environmental covenant restricting site use.
  2. Programmatic (Area-Wide) EHMP. Prepared for cases where widespread contamination is known or assumed to be present over a large area that crosses multiple land parcels. These often cover common/public areas or large state/county owned areas. Sites within a Programmatic EHMP Area may have Site-Specific EHMPs that supersede the Programmatic EHMP. Activities conducted within a Programmatic EHMP Area may require a Construction EHMP. COPCs identified in a Programmatic EHMP might not be present, or might not be adequately characterized, in all areas encompassed by the EHMP. Additional assessment could therefore be required prior to large-scale redevelopment activities.
  3. Construction EHMP. Prepared for sites where construction-activities will be conducted and contamination is still present. The EHMP is normally designed to protect site workers, prevent offsite migration of contamination or exacerbation of existing conditions and ensure that contaminated media is properly disposed or placed back on site and properly managed under an updated, Site-Specific EHMP. A Construction EHMP (C-EHMP) can supplement a Site-Specific or Programmatic EHMP or can be stand-alone in cases where site assessment and remediation are incomplete.

A more detailed discussion of each type of EHMP is provided below.

Return to the Top of the Page

19.6.1 BASIC COMPONENTS OF ALL EHMPS

Basic components of all EHMPs include:

  • Summary of site conditions, current/historical uses, past or ongoing environmental investigations. Summaries should be brief yet must include all pertinent information.
  • To-scale figures that clearly identify areas of known and suspected contamination.
  • Identification of all Contaminants of Potential Concern (COPCs). This should be based on all available data/information for the site. Discuss data gaps that should be considered when determining the COPCs.
  • Abbreviated Environmental Hazard Evaluation (EHE). An EHE is required prior to preparation of an EHMP, since the former serves as the basis for requirements in the latter. If a separate EHE has not been created, then one should be prepared following the guidelines in Section 13 and included as an appendix of the EHMP. The EHE should include:
    • Identification of all potential environmental concerns, as described in the HEER Office EHE guidance.
    • Identification of all potential current and future exposure to contamination by human or, as necessary, ecological receptors.
    • Evaluation of all hazards for all potential receptors. This should include evaluation of off-site residential receptors should soil potentially be transported off-site.
    • Use both site-specific Environmental Action Levels (EALs) and EALs for unrestricted use where groundwater is a potential drinking water resource and the nearest surface waterbody is less than 150 meters away (most restrictive, Tier 1 EALs).
    • Environmental Hazard Maps (i.e., to-scale maps that summarize the location and nature of potential environmental hazards at the site).
  • Engineering and Institutional Controls. Provide a discussion of engineering and/or institutional controls required to address identified environmental hazards and to eliminate exposure pathways (for example, cap, vapor mitigation system, annual inspection requirements, land use restrictions, etc.). Information to be provided includes:
    • Measures for repair or replacement of engineering controls that are disturbed or breached during future site activities.
    • Requirements for recurring (e.g., annual or more frequent) inspections of Institutional Controls to be submitted to HDOH.
  • Management of Contaminated Media. Discuss recommendations for proper handling and management of contaminated soil, groundwater, sediment and/or vapor that could be encountered during activities conducted at the site, including disposal requirements.
  • Health and Safety Measures. Provide a specific description of employee or construction worker protections and required notifications.
  • Long-term monitoring. Described long-term monitoring requirements for contaminated soil, groundwater and/or soil vapor.

For large, complex sites where significant public review is anticipated, a brief Fact Sheet that summarizes key elements of the EHMP in simple, non-technical terms will also be required.

Return to the Top of the Page

19.6.2 SITE-SPECIFIC EHMPS

Site-specific EHMPs are primarily prepared to document site conditions following the completion of a response action. The document provides guidance regarding long-term management of residual contamination at the site. Site-specific EHMPs are living documents and must be updated when conditions at the site change.

Evaluate response actions in accordance with the hierarchy of response action alternatives presented in Hawaiʻi Administrative Rules 11-451-8(c)(2). Note that reliance on engineering and/or institutional controls alone in the absence of physical treatment or removal of contamination is the least-preferred response action. Long-term management requirements imposed on the site are likely be required indefinitely, unless the contaminated media is treated or removed at a future date or naturally attenuates to below levels of potential concern. Be aware that this could affect future development of the property as well as the property value.

Determination of the exact magnitude and extent of contamination at a site and/or full cleanup temporarily might not be feasible due to on-going operations. When this is the case, a conservative estimate of the extent of contamination should be made and an interim site-specific EHMP prepared. Requirements in the interim EHMP should be adhered to until the contamination can be fully delineated and appropriately remediated. As site conditions change or new information becomes available, the interim EHMP is revised accordingly.

The property owner must discuss with the HEER Office whether an interim site-specific EHMP is appropriate for the site. HDOH-approved interim EHMPs may not be eligible to receive a No Further Action with Institutional Controls (NFA w/ICs) status if the site is not adequately characterized. However, they can still be protective of site users and provide a level of confidence to property owners and financial institutions, and therefore may be recommended by the HEER Office where conditions temporarily do not allow for completion of site investigation or remedial actions.

To ensure that future property owners are aware of, and comply with, requirements of the site-specific EHMP, it is recommended that an Environmental Covenant be registered with the Bureau of Conveyances and attached to the property title. This is especially important for non-petroleum sites, where potentially harmful levels of contaminants in soil or groundwater might not be obvious in the field. The Covenant should reference restrictions and requirements presented in the EHMP and note that the EHMP should be updated if conditions change.

Return to the Top of the Page

19.6.3 PROGRAMMATIC (AREA-WIDE) EHMPS

Programmatic or Area-wide EHMPs provide guidance for large areas or programs (e.g., specific entities and specific types of construction projects) where widespread contamination is known, suspected or could otherwise be encountered. Such EHMPs are usually prepared by HDOH or in close coordination with HDOH and do not supersede Site-specific EHMPs. The guidance provided typically addresses worker protection, soil management and disposal, hazard communication, and Best Management Practices (BMPs).

Programmatic and Area-wide EHMPs provide general guidance to manage contamination within the area(s), similar to a site-specific EHMP. The EHMPs often cover very large areas (e.g., Honolulu Harbor, Waikoloa Maneuver Area, Kahului Harbor Industrial District) or multiple areas under the oversight of a single entity (e.g., State-owned Airports). Contamination is often associated with from multiple sources and involves a variety of COPCs. The full extent and magnitude of contamination and might or might not have been delineated.

Programmatic and Area-wide EHMPs can normally be referred to for small-scale excavation activities and emergency repairs within the subject area or by the subject entity without the need for additional details. The property owner or operator should reach out to the HEER Office for guidance if a large-scale redevelopment will occur within an area covered by Programmatic or Area-wide EHMP. A Construction EHMP (or Construction EHMP addendum) will likely be required. In many cases, additional investigation activities will be cost-beneficial or even required to confirm the presence of COPCs and optimize contamination remediation and management actions.

Return to the Top of the Page

19.6.4 CONSTRUCTION EHMPS

Construction EHMPs are project-specific. The EHMP might be prepared for a project that is already covered by a site-specific or programmatic EHMP or at a site where a response action has yet to be completed and no other EHMP exists. Construction EHMPs are primarily prepared prior to conducting re-development or other construction activities and used to manage identified contamination during these activities. The EHMP includes the basic components of a site-specific EHMP (brief summary provided if latter is already available) but also includes specific details regarding management of contaminated media with respect to the particular construction project. These additional details should include, at a minimum:

  • Contact information for the developer, property owner, contractors, on-site qualified environmental professional, and any other pertinent personnel associated with the project;
  • Evaluation of planned construction materials with regards to known contaminants at the site (i.e., evaluating gaskets for storm drains or other utilities that may be degraded in contaminated groundwater):
    • Determine the compatibility of construction materials that are likely to be in contact with contaminated media;
    • Should construction materials not be in contact with contaminated media, or should the contaminants present at the site not pose any potential impacts to construction materials, then this should be stated in the EHMP;
  • Detailed description of types of planned construction activities;
  • Figure that illustrates the location of known or suspected contamination in relation to planned construction;
  • Specifics regarding soil reuse and disposal, including:
    • Planned re-use or disposal locations;
    • Volume of soil proposed for export;
    • Sampling methodology to characterize soil for re-use or disposal
      • COPCs and recommended laboratory test methods;
      • Recommended sample collection methods (Multi Increment samples collected in accordance with Sections 3, 4 and 5 of the HEER TGM required for final decision making purposes);
  • Specifics regarding any potential dewatering activities that may be conducted and associated requirements for groundwater disposal or re-infiltration;
  • Any other construction-related environmental information that may be relevant.

Construction EHMPs should be simple-to-understand guidance designed for use by the general contractor and sub-contractors at the project site. A template that can be used to help prepare an appropriate Construction EHMP for individual projects is available for download from the HEER website (https://health.hawaii.gov/heer/2020/02/05/revised-construction-ehmp-template-fact-sheet/). A template that can be used to prepare a Construction EHMP Addendum to an existing site-specific or programmatic EHMP is also available for download and sue. Contact the HEER Office to ensure you meet the qualifications before preparing and submitting an addendum EHMP, however (see below).

In some cases, contamination is identified during construction activities. Construction work that could encounter or otherwise disturb the contamination should cease immediately and the contamination reported to the appropriate entities, including the HEER Office. For more information on release reporting see Section 2.3.1.

The HEER Office will work with parties to determine whether additional investigation and/or remediation is required before construction activities in the affected area can restart. In some cases, the additional investigation can occur concurrent with or immediately following construction activities. In either case, an HDOH-approved, Construction EHMP will need to be prepared that outlines how workers will be protected and contaminated media will be managed in relation to the specific construction project prior to the restart of activities.

For some sites or areas that have existing HDOH-approved site-specific or programmatic/areawide EHMPs, the preparation of a separate, Construction EHMP for a project might not be necessary. If HDOH determines that the existing site-specific or programmatic/areawide EHMP is relevant and provides sufficient information, a Construction EHMP Addendum can be prepared for the project and attached to the existing site-specific or programmatic/areawide EHMP. The Construction EHMP Addendum provides project-specific details (e.g., soil sampling methods, soil and groundwater re-use/disposal requirements, points of contact for the project, etc.) that are not in the site-specific or areawide/programmatic EHMP. Prior to preparing a Construction EHMP Addendum, an Addendum Request Form must be completed and submitted to the HEER Office for approval.

For projects where contamination will remain on-site following a construction activity, additional site characterization and/or preparation of a site-specific EHMP for long-term management of the contamination will likely be required. If the site already has a site-specific EHMP, then the document should be updated as necessary following the completion of construction activities.

Return to the Top of the Page

19.7 INSTITUTIONAL AND ENGINEERING CONTROLS

Appropriate measures must be used to mitigate the environmental hazards posed by contaminated media left on site in restricted use closures. These measures are defined as institutional controls and engineering controls. Institutional controls are methods intended to prevent exposure to contaminated media by legal or procedural means (for example, environmental covenants), as opposed to engineering controls, which are methods of exposure prevention by physical means (for example, an active vapor mitigation system to prevent subsurface vapor intrusion into indoor air spaces).

Institutional controls alone are generally not sufficient to mitigate environmental hazards, with the exception of commercial or industrial zoned sites where representative sampling has demonstrated contaminant levels are above residential or unrestricted use EALs, but below applicable commercial/industrial use EALs. Engineering controls require institutional controls for their long-term management. Consequently, in most cases, institutional and engineering controls must be used together to adequately manage remaining environmental hazards at restricted use closure sites.

Return to the Top of the Page

19.7.1 INSTITUTIONAL CONTROLS

Institutional controls are legal or administrative measures that prevent exposure by influencing human behavior through laws, rules, permits, requirements, contracts, warnings, and advisories. Institutional controls help to minimize the potential for human exposure to contaminated media by controlling activities that may affect exposure. Institutional controls also restrict land use and on-site activity that might interfere with the containment of contaminated media left on site. Examples of institutional control measures include:

  • Prohibition on excavation of soil
  • Prohibition on use of groundwater
  • Prohibition on residential or other sensitive land use

HDOH’s primary legal instrument for establishing institutional and/or engineering controls at a site is the site closure document. HDOH may, at its discretion, require an environmental covenant to provide additional long-term protection for sites with significant and persistent contamination (see Subsection 19.8.1).

Return to the Top of the Page

19.7.2 ENGINEERING CONTROLS

Engineering controls are tangible measures that prevent exposure by physically preventing humans (or wildlife) from coming into contact with contaminated media left on site at restricted use closure sites. Institutional controls are required to ensure that engineering controls are properly managed. Examples of engineering controls include:

Soil Contamination

  • Capping systems – contaminated soil is covered with a cap to reduce surface-water infiltration and leaching, control gas and odor emissions, improve aesthetics, provide a stable surface over the contaminated soil, and prevent human exposure from direct contact. Caps can range from a simple native soil cover to single layer caps (e.g., asphalt/concrete and soil/bentonite/clay) to multi-layer cover systems (e.g., Resource Conservation and Recovery Act [RCRA] caps) to buildings or structures. Consideration must be given to the type, magnitude, and extent of contaminated soil when selecting the appropriate cap. A cap for soils contaminated with highly toxic and persistent contaminants should be highly durable and long lasting, such as a multi-layer cover system. Soil caps may be appropriate at certain sites where future development/construction is highly unlikely and institutional controls are used to restrict such land use. The soil cap thickness is determined considering site-specific factors but must be adequate to reduce or eliminate the environmental hazard(s). A visible marker, such as orange construction fencing, is generally used to mark the top of the contaminated soil layer. Soil caps are typically used for non-volatile contaminants where leaching is not a concern. If a structure is used as a cap, the permanence of the proposed building must be considered. For example, a high-rise structure designed and built for the long-term would be an appropriate “building cap” for significantly contaminated soils. The shorter life span of less durable structures must be taken into account when assessing long-term effectiveness of the cap.
  • On-site Encapsulation/Repository – for potentially mobile contaminants, soil is consolidated and encapsulated into a lined subsurface on-site cell or vault. Such systems are designed to eliminate or reduce surface-water infiltration and leaching, control gas and odor emissions, improve aesthetics, and prevent human and ecological exposure from direct contact. On-site repositories range from High Density Polyethylene (HDPE) liner encapsulation to subsurface concrete vaults. For non-mobile contaminants, unlined borrow pits may be adequate for on-site management.

Groundwater Contamination

  • Hydraulic Containment – measures are used to control the hydraulic gradient to minimize the spread of a groundwater plume. One example is the use of pumping wells to actively prevent the plume from spreading and reaching drinking water wells, surface water, or uncontaminated aquifers, etc. Another example is a slurry wall in which low permeability materials, such as grout, are injected into the subsurface to contain a groundwater plume. Institutional controls are necessary to restrict groundwater use.
  • Alternative Water Source – an alternative water source can be provided to an area where groundwater is contaminated and not suitable for ingestion. Institutional controls are necessary to restrict groundwater use.

Sediment Contamination

  • Capping systems – contaminated sediments are covered with a cap to eliminate erosion and dissolution into the water body, improve aesthetics, provide a stable surface over the contaminated sediment, and prevent human and ecological exposure from direct contact. An example is lining a streambed containing contaminated sediments with an impermeable material, such as HDPE liner, and then stabilizing the liner with highly durable materials, such as riprap and concrete.
  • Dredging – An ongoing dredging program can be used as an engineering control of contaminated sediments, as well.

Soil Vapor Contamination

  • Vapor barriers – impermeable materials are placed beneath a proposed building site to prevent subsurface vapor intrusion into indoor air spaces. Active vapor removal systems should be considered for sites with significant soil gas issues in which a gas collection system is placed beneath the barrier and connected to a suction fan, which may be vented above the roof of the building, or connected to a vapor treatment system such as a thermal oxidizer or granular activated carbon.

Return to the Top of the Page

19.8 LEGAL INSTRUMENTS FOR RESTRICTED USE CLOSURES

The primary legal instrument for establishing engineering and/or institutional controls at a site is the HDOH closure determination. Environmental covenants and land use restrictions listed in a LOC with Restrictions and noted on the property deed for sites in the VRP are another legal instrument for establishing institutional controls. At Department of Defense (DoD) Installation Restoration sites, Land Use Controls (LUCs) are implemented through a Land Use Controls Implementation Plan (LUCIP).

Return to the Top of the Page

19.8.1 UNIFORM ENVIRONMENTAL COVENANTS ACT (UECA) ENVIRONMENTAL COVENANT

The Uniform Environmental Covenants Act (UECA) is a Uniform Law that was approved by the Uniform Law Commission (also known as National Conference of Commissioners on Uniform State Laws) in 2003. The State of Hawaiʻi adopted the UECA as Senate Bill 1167 in 2006 [Hawaiʻi Revised Statutes (HRS), Chapter 508C (HRS 508C)]. The act is codified as HRS Chapter 508C. UECA establishes requirements for a new valid real estate document called an environmental covenant to control the future use of sites with contaminated media left on site when real estate is transferred from one person to another.

An environmental covenant is a legal device that restricts activities for sites where contaminated media is left on site. In such cases, institutional controls are needed to restrict land use to supplement the remedy and ensure safe land use. A UECA environmental covenant is based upon traditional property law principles and must be recorded in the local land records, thereby binding successive owners of the property. The State of Hawaiʻi has clear rights to enforce the land use restrictions under UECA covenants, ensuring with greater certainty the protection of human health and the environment throughout the life of the land use restriction and through real estate transactions or legal actions.

HDOH, at its discretion, may require UECA covenants. In general, these covenants are required for risk-based closures with extensive or highly persistent contamination. They may also be required where there are foreseeable future use changes that could expose sensitive populations.

An example UECA environmental covenant is provided in Subsection 18.6.5.

Return to the Top of the Page

19.8.2 VOLUNTARY RESPONSE PROGRAM (VRP) LETTER OF COMPLETION (LOC)

Site closure under the VRP (HRS 128D, Part II) is granted as a LOC. Under HRS 128D, Part II, a LOC is noted on the property deed and is sent to the county agency that issues building permits. The benefits and restrictions of the LOC “run with the land” and apply to all future owners of the property. Also see Subsections 19.2.3 and 19.3.2.

Return to the Top of the Page

19.8.3 DOD LAND USE CONTROLS IMPLEMENTATION PLANS (LUCIPS)

Under DoD guidance (DoD, 2001), LUCs may be placed on DoD real property because of environmental restoration concerns. The Installation must then develop an implementation plan for the LUCs. A LUCIP is a DoD internal management tool that explains how LUCs will be established and identifies the individual(s) responsible for their maintenance and management. The LUCIP is incorporated in the DoD Installation Master Plan (DoD, 2001). DoD guidance (DoD, 2001) mandates that if a property subject to LUCs is transferred from federal ownership, the LUCs must be incorporated into the property transfer documents. Specifically, necessary language for the LUCs must be drafted, such as deed restrictions or restrictive covenants (DoD, 2001).

During the time the federal government owns a property subject to LUCs, the HDOH has agreed that DoD LUCIPs will be sufficient to comply with the UECA (HDOH, 2007b). In other words, as long as the DoD LUCs are clearly identified and observed pursuant to DoD policy (through the use of a LUCIP), the HDOH does not require that DoD place UECA covenants on federally owned property. For Installation Restoration sites, the DoD must, however, provide the HDOH with information including (1) the site location, (2) the specific LUCs at the site, and (3) other reasonably available information regarding the site requested by the HDOH. The site will then be included in the HDOH registry of sites with land use restrictions. This provision is not currently required for active installations (HDOH, 2007b).

If a property that is subject to LUCs is transferred from federal ownership, the DoD must execute a restrictive covenant regarding the LUCs in a form acceptable to the HDOH. The restrictive covenant must be recorded on the title of the property.

Return to the Top of the Page

19.8.4 PROPERTY TRANSFERS AND SITE CLOSURES WITH USE RESTRICTIONS

All sites closed with restrictions require ongoing participation from the property owner to maintain safe use of the property, and prevent remedy failure. Therefore, HDOH strongly recommends that residual contamination and required institutional and/or engineering controls be freely disclosed to potential purchasers prior to property transfer.